By the Numbers
Updated: July 2024 Total cost: $257.7 million Project completion: Third quarter 2026 Potential community economic impact: $400 million [source: South Bend Regional Chamber] Number of
Updated: July 2024 Total cost: $257.7 million Project completion: Third quarter 2026 Potential community economic impact: $400 million [source: South Bend Regional Chamber] Number of
Beacon Health System Jeff Costello, Chief Financial OfficerJeff’s career at Beacon spans over 36 years, including serving as Chief Financial Officer of Memorial Health System
Updated: July 2024 New Memorial Patient Bed Tower timeline: 2024 milestones June – Install auger piles in building footprint July – Install tower crane base
The realities and limitations of the aging patient care towers at Memorial Hospital started a movement to make a change for the better. A big