Updated: July 2024
New Memorial Patient Bed Tower timeline:
2024 milestones
- June – Install auger piles in building footprint
- July – Install tower crane base to prepare for erection of structural steel
- August – Install earth retention system | Begin steel erection over Memorial Leighton Heart and Vascular Center
- October – Begin steel erection and pour slab on grade
2025 milestones
February – Enclosure work begins
2026 milestones
Third quarter: Completion of new Patient Bed Tower
Completed enabling projects
Prior to construction of the new Memorial Hospital Patient Bed Tower, two large-scale enabling projects needed to be completed: the Energy Center addition that provides additional mechanical systems infrastructure and the complete renovation of an existing Patient Care Floor (6th floor Acute Care).
- August 2023: 6th floor renovation is complete. Learn more: Memorial Hospital celebrates milestone in campus revitalization, Patient Tower plans
- September 2023: Initiated new boilers and decommissioned old boilers. Learn more: Memorial Hospital Energy Center plans